Violation Detail
Standard Cited: 19100119 L01 Process safety management of highly hazardous chemicals.
Inspection Nr: 1183959.015
Citation: 02001
Citation Type: Other
Abatement Date: 3
Initial Penalty: $49,797.00
Current Penalty: $0.00
Issuance Date: 04/06/2017
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC):
Gravity:
Report ID: 0213900
Contest Date:
Final Order: 04/28/2017
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 04/28/2017 | $0.00 | Other | ||
Penalty | Z: Issued | 04/06/2017 | $49,797.00 | Repeat |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1910.119(l)(1): The employer did not establish written procedures to manage changes to process chemicals, technology, equipment, and procedures, and changes to facilities that affect a covered process: a) Aramids Phosgene unit 1074: The employer failed to implement procedures to manage changes that affect the covered process when an alternate method was used to purge phosgene from the RE-1 reactor, on or about 10/7/16. E.I. DuPont DeNemours Inc was previously cited for a violation of this occupational safety and health standard or its equivalent standard 29 CFR 1910.119(l)(1), which was contained in OSHA inspection number 977053, citation number 1, item number 4 and was affirmed as a final order on 3/28/16, with respect to a workplace located at 3460 Highway 44 Darrow Louisiana 70725.