Violation Detail
Standard Cited: 19100036 G04 Design and construction requirements for exit routes.
Inspection Nr: 1103274.015
Citation: 02001
Citation Type: Other
Abatement Date: 11/27/2015 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 11/12/2015
Nr Instances: 1
Nr Exposed: 11
Related Event Code (REC):
Gravity:
Report ID: 0830600
Contest Date: 12/03/2015
Final Order: 06/30/2016
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | R: Review Commission | 06/30/2016 | $0.00 | 11/27/2015 | Other | |
Penalty | C: Contested | 12/03/2015 | $0.00 | 11/27/2015 | Other | |
Penalty | Z: Issued | 11/12/2015 | $0.00 | 11/27/2015 | Other |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1910.36(g)(4): Objects that projected into the exit route reduced the width of the exit route to less than the 28 inches minimum width requirements for exit routes: (a) On or about November 2, 2015, and at times prior, the employer did not ensure employees were protected from fire and smoke inhalation hazards in that the exit path out of the employee locker area was obstructed by boxes, and the exit path out of the extra tire storage/employee break area on the second floor was obstructed by stacked tires. Abatement Note: Abatement certification is required for this item (see enclosed "Certification of Corrective Action Worksheet").