Violation Detail
Standard Cited: 19100303 E01 II General.
Inspection Nr: 1019812.015
Citation: 02001
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 05/04/2015
Nr Instances: 1
Nr Exposed: 25
Abatement Date: 05/13/2015
Gravity:
Report ID: 0728500
Contest Date:
Final Order: 06/04/2015
Related Event Code (REC): A
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 06/04/2015 | $0.00 | 05/13/2015 | Other | |
| Penalty | Z: Issued | 05/04/2015 | $0.00 | 05/13/2015 | Other |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1910.303(e)(1)(ii): Markings were not provided on electrical equipment giving voltage, current, wattage, and other ratings as necessary: (a) On or about January 21, 2015, in the north side of building #2 of the facility, the employer did not ensure that Pendant Control Station for the Eastern Overhead Bridge Crane had a UL Plate that clearly showed the markings for the voltage, current, wattage and other required information per the standard. Abatement certification is required for this item; use the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET for this purpose.