Violation Detail

Standard Cited: 19100107 B05 I Spray finishing using flammable and combustible materials.

Inspection Nr: 1009419.015

Citation: 02001

Citation Type: Other

Abatement Status: Corrected During Inspection

Initial Penalty: $0.00

Current Penalty: $0.00

Issuance Date: 03/10/2015

Nr Instances: 1

Nr Exposed: 3

Abatement Date:

Gravity:

Report ID: 0418800

Contest Date:

Final Order: 03/31/2015

Related Event Code (REC):

Emphasis:


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty I: Informal Settlement 03/31/2015 $0.00   Other  
Penalty Z: Issued 03/10/2015 $0.00   Other  

Text For Citation: 02 Item/Group: 001 Hazard:

29 CFR 1910.107(b)(5)(i): Visible gauges, audible alarms, or pressure activated devices were not installed to indicate or insure that the required air velocity was maintained: On or about November 20, 2015 at the above addressed job site, employees performing spray painting operation in Binks Manufacturing Company Standard AA-510-530-550-T paint booth, working with flammable chemicals such as but not limited to, Whitaker Oil Company #48 Lacquer Thinner, were exposed to fire hazards due to manometer on paint booth not in service.

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.