Violation Detail
Standard Cited: 19100119 F01 IV Process safety management of highly hazardous chemicals.
Inspection Nr: 451379.015
Citation: 01034
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $7,000.00
Current Penalty: $7,000.00
Issuance Date: 11/26/2012
Nr Instances: 9
Nr Exposed: 160
Abatement Date: 02/27/2013
Gravity: 10
Report ID: 0522500
Contest Date: 12/12/2012
Final Order: 03/10/2014
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 03/10/2014 | $7,000.00 | 02/27/2013 | Serious | |
| Penalty | C: Contested | 12/19/2012 | $7,000.00 | 02/27/2013 | Serious | |
| Penalty | Z: Issued | 11/26/2012 | $7,000.00 | 02/27/2013 | Serious |
Text For Citation: 01 Item/Group: 034 Hazard:
29 CFR 1910.119(f)(1)(iv): The employer shall develop and implement written operating procedures that provide clear instructions for safely conducting activities involved in each covered process consistent with the process safety information and shall address at least the following elements: Safety systems and their functions: Written operating procedures did not include safety systems and their functions, including but not limited to rupture disks, pressure relief valves, interlocked controls, and DCS controls for the following procedures: a. PHOS SOPM 410, Production of 9228 in 32R. b. PHOS SOPM 303, 44R Doverphos DP10 Production. c. PHOS SOPM 206, Changing Filter for 44Rx and 75Rx. d. PHOS SOPM 208, Charging Phenol to 75Rx. e. PHOS SOPM 301, 51R Doverphos DP4 Production. f. PHOS SOPM 304, 75R Doverphos DP4 Production. g. PHOS SOPM 310, Hipure Unit Operation. h. PHOS SOPM 404, Charging Reactors. i. PHOS SOPM 409, 9228 Production in 36R (PCL3 process).
Translate