Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 314928060
Citation: 01032A
Citation Type: Serious
Abatement Status: X
Initial Penalty: $4,900.00
Current Penalty: $3,000.00
Issuance Date: 04/08/2011
Nr Instances: 1
Nr Exposed: 26
Abatement Date: 11/01/2011
Gravity: 10
Report ID: 0627700
Contest Date:
Final Order:
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 04/27/2011 | $3,000.00 | 11/01/2011 | Serious | |
| Penalty | Z: Issued | 04/08/2011 | $4,900.00 | 04/27/2011 | Serious |
Text For Citation: 01 Item/Group: 032A Hazard: CHEMNEP
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed: The employer does not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirements of the standard were being followed. This violation occurred on October 20, 2010 and at times prior thereto. Pursuant to 29 C.F.R. 1903.19, within ten (10) calendar days of the date of this citation, the employer must submit documentation showing that it is in compliance with the standard regarding at least annual periodic inspections of energy control procedures. A method of abatement is to perform periodic inspections at least annually of the energy control procedures and certify that the period inspection were preformed as per 29 CFR 1910.147(c)(6)(i)A through (D) and 29 CFR 1910.147(c)(6)(ii).