Violation Detail
Standard Cited: 19100119 F01 I D Process safety management of highly hazardous chemicals.
Inspection Nr: 451379.015
Citation: 01029
Citation Type: Serious
Abatement Date: 09/30/2014 2
Initial Penalty: $7,000.00
Current Penalty: $7,000.00
Issuance Date: 11/26/2012
Nr Instances: 4
Nr Exposed: 87
Related Event Code (REC):
Gravity: 10
Report ID: 0522500
Contest Date: 12/12/2012
Final Order: 03/10/2014
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 03/10/2014 | $7,000.00 | 09/30/2014 | Serious | |
Penalty | C: Contested | 12/19/2012 | $7,000.00 | 02/27/2013 | Serious | |
Penalty | Z: Issued | 11/26/2012 | $7,000.00 | 02/27/2013 | Serious |
Text For Citation: 01 Item/Group: 029 Hazard:
29 CFR 1910.119(f)(1)(i)(D): The employer shall develop and implement written operating procedures that provide clear instructions for safely conducting activities involved in each covered process consistent with the process safety information and shall address at least the following elements: Emergency shutdown including the conditions under which emergency shutdown is required, and the assignment of shutdown responsibility to qualified operators to ensure that emergency shutdown is executed in a safe and timely manner: a. In the chlorination department 1C building #17, the employer failed to develop and implement written emergency shutdown procedures, that included shutdown conditions and assignments of responsibility. b. In the phosphites plant building #27, the employer failed to develop and implement written emergency shutdown procedures for conditions other than power failure and PHOS SOPM 152, Power Failure Emergency Shutdown, emergency shutdown procedures failed to include emergency shutdown conditions and assignments of responsibility. c. In the chlorination department 1P building #6, the employer failed to develop and implement written emergency shutdown procedures that included shutdown conditions and assignments of responsibility. d. In chlorination department 1C, there were two emergency shutdown for power failure procedures for 20R reactor with conflicting instructions.