Violation Detail
Standard Cited: 19100119 J04 I Process safety management of highly hazardous chemicals.
Inspection Nr: 311917009
Citation: 01022
Citation Type: Serious
Abatement Status: X
Initial Penalty: $5,000.00
Current Penalty: $5,000.00
Issuance Date: 05/13/2009
Nr Instances: 2
Nr Exposed: 18
Abatement Date: 06/29/2009
Gravity: 10
Report ID: 0213400
Contest Date: 06/03/2009
Final Order: 12/24/2009
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | R: Review Commission | 12/24/2009 | $5,000.00 | 06/29/2009 | Serious | |
| Penalty | J: ALJ Decision | 08/28/2009 | $5,000.00 | 06/29/2009 | Serious | |
| Penalty | Z: Issued | 05/13/2009 | $5,000.00 | 06/29/2009 | Serious |
Text For Citation: 01 Item/Group: 022 Hazard: REFINERY
29 CFR 1910.119(j)(4)(i): Inspections and tests were not performed on process equipment to maintain its mechanical integrity: a- Hess Port Reading Refinery, Dimersol - Rupture disks (RD) and associated tell tale pressure gauges were not inspected on process equipment to include but not limited to the S-2204A Stabilizer Feed Filter, D-2201 Caustic Wash Drum and D-2213 Ammonia Mix Drum. Tell tales/pressure gauges for RDs on the D-2202 Water Wash Drum and D-2203 Stabilizer Surge Drum were unreadable as they were etched and clouded over. Conditions noted on or about 03/05/09 and 03/31/09. b- Hess Port Reading Refinery, Gas Con - Readings were not taken at specified active thickness measurement locations (TMLs) for the T-622 Deethanizer. Condition noted on or about 02/20/09.
Translate