Standard Cited: 19100119 M04 II Process safety management of highly hazardous chemicals.
Inspection Nr: 1117233.015
Citation: 01021C
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $3,500.00
Current Penalty: $0.00
Issuance Date: 05/06/2016
Nr Instances: 2
Nr Exposed: 40
Abatement Date: 12/29/2017
Gravity: 5
Report ID: 0522500
Contest Date: 05/18/2016
Final Order: 10/16/2017
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 10/16/2017 | $0.00 | 12/29/2017 | Serious | |
Penalty | C: Contested | 05/26/2016 | $3,500.00 | 06/10/2016 | Serious | |
Penalty | Z: Issued | 05/06/2016 | $3,500.00 | 06/10/2016 | Serious |
Text For Citation: 01 Item/Group: 021C Hazard:
29 CFR 1910.119(m)(4): A report shall be prepared at the conclusion of the investigation which includes at a minimum: 29 CFR 1910.119(m)(4)(ii): Date investigation began: a. On or about January 28, 2016, the incident investigation report for the incident, which occurred on or about December 16, 2015, and involved pump, PC-6101, that did not shutdown after suction valve, YV-61115, failed closed, did not include the date the investigation began. b. On or about November 20, 2015, the incident investigation report for the incident, which occurred on or about August 12, 2014, and involved a regeneration fluid (ethanol/water mixture) release in the DD&E building, did not include the date the investigation began.