Violation Detail
Standard Cited: 19100303 B08 III General.
Inspection Nr: 1342920.015
Citation: 01020B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 02/25/2019
Nr Instances: 3
Nr Exposed: 7
Abatement Date: 11/13/2020
Gravity: 1
Report ID: 0627500
Contest Date: 03/15/2019
Final Order: 09/27/2020
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 09/27/2020 | $0.00 | 11/13/2020 | Serious | |
| Penalty | C: Contested | 03/19/2019 | $0.00 | 03/14/2019 | Serious | |
| Penalty | Z: Issued | 02/25/2019 | $0.00 | 03/14/2019 | Serious |
Text For Citation: 01 Item/Group: 020B Hazard:
29 CFR 1910.303(b)(8)(iii): Electric equipment provided with ventilating openings was installed so that walls or other obstructions prevent the free circulation of air through the equipment: On or about August 28, 2018, on the production floor; employees were exposed to fire/burn and electrical shock hazards due to the possibility of the transformers overheating. The ventilation openings in the back were blocked by the walls which prevented the free circulation of air through the equipment. There were three instances: a) A 220v Square D transformer located in the taco shell area. b) A second 220v Square D transformer located in the taco shell area . c) A 220v General Electric transformer located in the electrical shop.
Translate