Violation Detail
Standard Cited: 19100303 F02 General.
Inspection Nr: 1298240.015
Citation: 01020
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $8,315.00
Current Penalty: $8,315.00
Issuance Date: 08/16/2018
Nr Instances: 3
Nr Exposed: 10
Abatement Date: 09/05/2018
Gravity: 5
Report ID: 0522500
Contest Date: 09/18/2018
Final Order: 08/07/2019
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 08/07/2019 | $8,315.00 | 09/05/2018 | Serious | |
Penalty | C: Contested | 09/19/2018 | $8,315.00 | 09/05/2018 | Serious | |
Penalty | Z: Issued | 08/16/2018 | $8,315.00 | 09/05/2018 | Serious |
Text For Citation: 01 Item/Group: 020 Hazard:
29 CFR 1910.303(f)(2): Services, feeders, and branch circuits. Each service, feeder, and branch circuit, at its disconnecting means or overcurrent device, shall be legibly marked to indicate its purpose, unless located and arranged so the purpose is evident: a. On or about April 19, 2018, located in the Vulcanizing Department, there was a 480 electrical panel box that was not marked to indicate the purpose of each breaker, thereby exposing the employees to the hazards associated with the equipment supplied by breaker box. b. On or about April 19, 2018, located in the Lab, there were two breaker boxes that did not have labeling for the electrical panel boxes along the center of the wall behind the oven to identify the purpose of the breakers, thereby exposing the employees to the hazards associated with the equipment supplied by the breaker boxes.