Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 314061896
Citation: 01019
Citation Type: Serious
Abatement Status: X
Initial Penalty: $5,000.00
Current Penalty: $3,500.00
Issuance Date: 01/23/2012
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 08/31/2012
Gravity: 05
Report ID: 0728900
Contest Date:
Final Order:
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 02/09/2012 | $3,500.00 | 08/31/2012 | Serious | |
| Penalty | Z: Issued | 01/23/2012 | $5,000.00 | 02/24/2012 | Serious |
Text For Citation: 01 Item/Group: 019 Hazard: CHEMNEP
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed: Throughout the Facility: The employer failed to conduct a periodic inspection of the energy control procedures as outlined in the standard. Abatement certification is required for this violation. The abatement certification sheet is enclosed with the citations.