Violation Detail

Standard Cited: 19100119 L04 Process safety management of highly hazardous chemicals.

This violation item has been deleted.

Inspection Nr: 313008674

Citation: 01019

Citation Type: Serious

Abatement Status:

Initial Penalty: $4,500.00

Current Penalty:

Issuance Date: 10/13/2009

Nr Instances: 1

Nr Exposed: 23

Abatement Date: 11/06/2009

Gravity: 10

Report ID: 0213900

Contest Date: 10/28/2009

Final Order: 04/22/2010

Related Event Code (REC):

Emphasis:


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty R: Review Commission 04/22/2010 11/06/2009 Serious  
Penalty Z: Issued 10/13/2009 $4,500.00 11/06/2009 Serious  

Text For Citation: 01 Item/Group: 019 Hazard: REFINERY

29 CFR 1910.119(l)(4): A change covered by 29 CFR 1910.119(l) resulted in a change in the process safety information required by 29 CFR 1910.119(d) and the process information was not updated: a) Nustar Asphalt Refining Co. LLC, Paulsboro facility - The employer did not document and update the process safety information when there was a change in alarm set points on PI-622 (pressure indicator) was changed from 14.0 to 17.0, in the distributive control system (DCS) for Unit 2. This is a change of process safety information as described in paragraph d of this section (d)(2)(i)(H). On or about 7/29/09. b). Nustar Asphalt Refining Co. LLC, Paulsboro facility - The employer did not document and update the process safety information when there was a change in alarm set points on the 6-BTU-849 high alarm (heat control) was changed from 106.000 to 107,5000 BTU in the distributive control system (DCS) for Unit 2. This is a change of process safety information as described by paragraph d of this section (d)(2)(i)(H). On or about 7/29/09. c). Nustar Asphalt Refining Co. LLC, Paulsboro facility - The employer did not document and update the process safety information when there was a change in alarm set points on LI-106 (level indicator) from 55 to 70 in the distributive control system (DCS) in Unit 2. This is a change of process safety information as described in paragraph (d)(2)(i)(H) of this section. On or about 7/29/09. NOTE: IN ADDITION TO ABATEMENT CERTIFICATION, THE EMPLOYER IS REQUIRED TO SUBMIT ABATEMENT DOCUMENTATION FOR THIS ITEM, FAILURE TO COMPLY WILL RESULT IN AN ADDITIONAL PENALTY OF $1000.00 IN ACCORDANCE WITH 29 CFR 1903.19.

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.