Standard Cited: 19100333 B02 Selection and use of work practices
Inspection Nr: 1023693.015
Citation: 01017B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 07/30/2015
Nr Instances: 1
Nr Exposed: 5
Abatement Date: 09/16/2015
Gravity: 10
Report ID: 0523400
Contest Date: 08/20/2015
Final Order: 01/22/2016
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 01/22/2016 | $0.00 | 09/16/2015 | Serious | |
Penalty | C: Contested | 08/25/2015 | $0.00 | 09/16/2015 | Serious | |
Penalty | Z: Issued | 07/30/2015 | $0.00 | 09/16/2015 | Serious |
Text For Citation: 01 Item/Group: 017B Hazard:
29 CFR 1910.333(b)(2): While an employee was exposed to contact with parts of fixed electric equipment or circuits which were deenergized, the circuits energizing the parts were not locked out or tagged or both in accordance with the requirements of this paragraph (b) of 29 CFR 1910.333(b)(2): (a) On or about February 10, 2015 maintenance employees conducted electrical trouble shooting on wringer number two (2) main disconnect to verify fuse continuity. Employees did not lockout the main disconnect isolating device while conducting the continuity tests, exposing employees to an electrical shock and arc flash hazard.