Standard Cited: 19100303 B08 I General.
Inspection Nr: 1745840.015
Citation: 01017
Citation Type: Serious
Abatement Status:
Initial Penalty: $10,372.00
Current Penalty: $10,372.00
Issuance Date: 10/10/2024
Nr Instances: 3
Nr Exposed: 6
Abatement Date: 11/06/2024
Gravity: 5
Report ID: 0625400
Contest Date: 11/06/2024
Final Order:
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | C: Contested | 02/12/2025 | $10,372.00 | 11/06/2024 | Serious | |
Penalty | Z: Issued | 10/10/2024 | $10,372.00 | 11/06/2024 | Serious |
Text For Citation: 01 Item/Group: 017 Hazard:
29 CFR 1910.303(b)(8)(i): Electrical equipment was not firmly secured to the surface on which it was mounted: Production Department: On or about May 8, 2024, and at times prior thereto, electrical equipment was not firmly secured to the surface in which it was mounted while employees used the Top Master #289, Injection Molder #3, and the CNC #166.