Violation Detail
Standard Cited: 19100303 B01 General.
Inspection Nr: 1189968.015
Citation: 01017
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $2,897.00
Current Penalty: $869.00
Issuance Date: 04/21/2017
Nr Instances: 5
Nr Exposed: 4
Abatement Date: 05/03/2017
Gravity: 5
Report ID: 0215800
Contest Date: 05/09/2017
Final Order: 03/16/2018
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 03/16/2018 | $869.00 | 05/03/2017 | Serious | |
Penalty | C: Contested | 05/16/2017 | $2,897.00 | 05/03/2017 | Serious | |
Penalty | Z: Issued | 04/21/2017 | $2,897.00 | 05/03/2017 | Serious |
Text For Citation: 01 Item/Group: 017 Hazard:
29 CFR 1910.303(b)(1): Electrical equipment was not free from recognized hazards that were likely to cause death or serious physical harm to employees: a) On or about 11/8/2016, In the facility: The Tumbler had an unused interlock circuit which was left hanging from the bottom of the machine, with metal washers weighing it down. b) On or about 11/8/2016, In the facility: The Tumbler had a metal condulete box with a flexible cord leading from it, the cord was pulled away from the condulete box. c) On or about 11/8/2016, In the facility: The Tumbler had metal condulete boxes with rigid conduit pulled away from the boxes, exposing wiring. d) On or about 11/8/2016, In the facility: The Tumbler had a splice in its supply line which was made outside of a rigid box. e) On or about 11/8/2016, In the facility: The foot control for power press number seven had a damaged electrical cable. Abatement certification is required for this item.