Violation Detail
Standard Cited: 19100219 E03 I Mechanical power-transmission apparatus.
Inspection Nr: 1350744.015
Citation: 01016B
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 03/26/2019
Nr Instances: 3
Nr Exposed: 3
Abatement Date:
Gravity: 5
Report ID: 0215800
Contest Date: 04/11/2019
Final Order: 09/16/2019
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 09/16/2019 | $0.00 | Serious | ||
| Penalty | C: Contested | 04/15/2019 | $0.00 | Serious | ||
| Penalty | Z: Issued | 03/26/2019 | $0.00 | Serious |
Text For Citation: 01 Item/Group: 016B Hazard:
29 CFR 1910.219(e)(3)(i): Vertical or inclined belt(s) were not enclosed by guard(s) conforming to the requirements specified at 29 CFR 1910.219(m) and (o): a) Bldg. 66-1, on or about 10/10/18: V belt driving the Trane Climate Changer AC unit for the mezzanine #W0093 was not adequately guarded in that the inside portion next to motor was not guarded. b) Bldg. 48-2, Cutter/Grind, on or about 10/16/18: A grooved belt driving the Hybco grinder #39392 was not guarded. c) Bldg. 48-3, on or about 10/23/18: Belt drive on the New Transfer machine #34301 at machining head #1 was not guarded at the inside portion.