Powered by GoogleTranslate

Violation Detail

Standard Cited: 5A0001 OSH Act General Duty Paragraph

Inspection Nr: 307528984

Citation: 01015

Citation Type: Serious

Abatement Status: X

Initial Penalty: $1,875.00

Current Penalty: $1,125.00

Issuance Date: 07/21/2005

Nr Instances: 17

Nr Exposed: 21

Abatement Date: 08/08/2005

Gravity: 03

Report ID: 0830500

Contest Date: 08/03/2005

Final Order: 12/05/2005

Related Event Code (REC):

Emphasis:


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty F: Formal Settlement 12/05/2005 $1,125.00 08/08/2005 Serious  
Penalty Z: Issued 07/21/2005 $1,875.00 08/08/2005 Serious  

Text For Citation: 01 Item/Group: 015 Hazard: STRUCK BY

Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish a place of employment which was free from recognized hazards that were causing or likely to cause death or serious physical harm to employees in that employees were exposed to struck by hazards: (a)AFCO Steel LLC at 31455 County Road 39 1/2, Greeley, CO 80631: On or before 03/16/05, the employer did not conduct annual or periodic inspections of the 17 overhead wall jib cranes. As a result, there was no assurance that these cranes, which were used to lift steel and other materials, were in good working order. For example, one jib crane, located near the steel staging area, included a deformed hook, another hook was missing its safety latch, and this crane did not have its rated load capacity stated on it. Moreover, there were no records of inspection. Condition exposed employees to struck by hazards. Abatement Note: Abatement certification and documentation are required for this item (see enclosed "Sample Abatement-Certification Letter"). Among other methods, one feasible and acceptable abatement method included conducting periodic inspections, and keeping records of such inspections, in accordance with American National Standards Institute (ANSI) B30.11, "Monorails and Underhung Cranes," and ANSI B30.16, "Overhead Hoists": ANSI B30.11 - 1980 Section 11-2.1.3 provides that the hoist inspection shall be conducted in accordance with ANSI B30.16 - 1973. In addition, ANSI B30.11 provides that a complete inspection of normal service equipment shall be done annually, and specifically lists inspection items to address. Moreover, ANSI B30.11 Section 11-2.1.4 provides that equipment which is used for standby service shall also be inspected annually. Section 11-2.1.5 provides that dated evidence of the inspection of critical items shall be maintained.

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.