Violation Detail
Standard Cited: 19100303 B07 IV General.
Inspection Nr: 1229034.015
Citation: 01015
Citation Type: Serious
Abatement Date: 09/25/2018 2
Initial Penalty: $12,675.00
Current Penalty: $4,125.00
Issuance Date: 10/31/2017
Nr Instances: 2
Nr Exposed: 9
Related Event Code (REC):
Gravity: 10
Report ID: 0418100
Contest Date: 11/23/2017
Final Order: 09/04/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 09/04/2018 | $4,125.00 | 09/25/2018 | Serious | |
Penalty | C: Contested | 12/13/2017 | $12,675.00 | 11/28/2017 | Serious | |
Penalty | Z: Issued | 10/31/2017 | $12,675.00 | 11/28/2017 | Serious |
Text For Citation: 01 Item/Group: 015 Hazard:
29 CFR 1910.303(b)(7)(iv): There were damaged parts that may adversely affect safe operation or mechanical strength of the equipment, such as parts that were broken, bent, cut or deteriorated by corrosion, chemical action or overheating. On 5/2/17, at the Buford facility, maintenance employees were exposed to 480 volt electrical hazards as they routinely accessed high voltage electrical-panels that had damaged doors that prevented the panels from being turned off.