Violation Detail
Standard Cited: 19100305 B02 I Wiring methods, components, and equipment for general use.
Inspection Nr: 313357089
Citation: 01014B
Citation Type: Serious
Abatement Status: X
Initial Penalty:
Current Penalty:
Issuance Date: 03/28/2011
Nr Instances: 3
Nr Exposed: 8
Abatement Date: 04/21/2011
Gravity: 05
Report ID: 1032500
Contest Date:
Final Order:
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 04/18/2011 | 04/21/2011 | Serious | ||
| Penalty | Z: Issued | 03/28/2011 | 04/21/2011 | Serious |
Text For Citation: 01 Item/Group: 014B Hazard: CHEMNEP
29 CFR 1910.305(b)(2)(i): All pull boxes, junction boxes, and fittings were not provided with covers identified for the purpose. a)LPR Storage, LPR 005: On or about October 4, 2010 and at times prior thereto, the cover of an electrical elbow was not properly closed exposing insulated conductors. b)Interstitial space above red hallway: On or about October 4, 2010 and at times prior thereto, insulated conductors protruded from an uncovered junction box. c)Sump room: On or about December 8, 2010 and at times prior thereto, the lighting snap switch was removed, but the face place still had the switch opening exposing live conductors. Note: Abatement certification is required for this item.