Violation Detail
Standard Cited: 19100303 B01 General.
Inspection Nr: 930829.015
Citation: 01014A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $5,500.00
Current Penalty: $4,400.00
Issuance Date: 02/12/2014
Nr Instances: 1
Nr Exposed: 5
Abatement Date: 03/11/2014
Gravity: 5
Report ID: 0419700
Contest Date: 03/05/2014
Final Order: 07/10/2015
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 07/10/2015 | $4,400.00 | 03/11/2014 | Serious | |
| Penalty | C: Contested | 12/19/2014 | $5,500.00 | 03/11/2014 | Serious | |
| Penalty | Z: Issued | 02/12/2014 | $5,500.00 | 03/11/2014 | Serious |
Text For Citation: 01 Item/Group: 014A Hazard:
29 CFR 1910.303(b)(1): Electrical equipment was not free from recognized hazards that were likely to cause death or serious physical harm to employees, in that the employer did not ensure the safety of the equipment pursuant to the considerations in sections (i) through (viii) of 29 CR 1910.303(b)(1): a. On or about August 16, in the west wire bay, the MEP-1 electrical disconnect switch was not apporved for its purpose, exposing employees to an electrical hazard.
Translate