Violation Detail
Standard Cited: 19100305 A02 X Wiring methods, components, and equipment for general use.
Inspection Nr: 1766560.015
Citation: 01014A
Citation Type: Serious
Abatement Status:
Initial Penalty: $16,550.00
Current Penalty: $11,000.00
Issuance Date: 02/04/2025
Nr Instances: 12
Nr Exposed: 50
Abatement Date: 10/09/2025
Gravity: 10
Report ID: 0728900
Contest Date: 02/19/2025
Final Order: 08/27/2025
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | P: Petition to Mod Abatement | 09/15/2025 | $11,000.00 | 10/09/2025 | Serious | |
Penalty | F: Formal Settlement | 08/27/2025 | $11,000.00 | 08/25/2025 | Serious | |
Penalty | C: Contested | 02/20/2025 | $16,550.00 | 03/03/2025 | Serious | |
Penalty | Z: Issued | 02/04/2025 | $16,550.00 | 03/03/2025 | Serious |
Text For Citation: 01 Item/Group: 014A Hazard:
29 CFR 1910.305(a)(2)(x):Flexible cords were not protected from accidental damage, as might be caused for example, by sharp corners, projections, and doorways or other pinch points: On or about August 5th, 2024, employees engaged in commercial bakery production activities located at 4657 G Street, Omaha, Nebraska 68117, were exposed to electrical and fire hazards in that damaged flexible cords were being used in production. The employer failed to protect flexible cords from damage. Instances of failure include but are not limited to: a) 2 damaged flexible cords inserted into Power Flex 40 - White Packaging Production Line. b) 2 damaged suspended flexible cords - White Packaging Production Line. c) 1 damaged flexible cord inserted into Power Flex 4 - White Packaging Production Line. d) 1 damaged flexible cord inserted into Power Flex 40 - Blue Line next to the Blue Oven. e) 2 damaged flexible cords inserted into Power Flex 40 and Icing Control junction Box - Line #2. f) 1 damaged flexible cord inserted into Baldor motor - Oven #2 Feed Conveyor. g) 1 damaged flexible cord inserted into motor - Pan return #1 conveyor. h) 1 damaged suspended flexible cord - Red Moline Line. i) 1 damaged flexible cord inserted into Baldor motor - Red Moline Line. j) 1 damaged flexible cord inserted into junction box under conveyor next to the icing tank - Panning Line. k) 2 damaged flexible cords inserted into Power Flex 40 - Mounted on side of conveyor next to Refrigeration Spiral #2 door. l) 1 damaged flexible cord inserted into white motor - Mounted on side of conveyor next to Power Flex 40 - Next Refrigeration Spiral #2 door.