Violation Detail
Standard Cited: 19100219 C02 II Mechanical power-transmission apparatus.
Inspection Nr: 1206035.015
Citation: 01014A
Citation Type: Serious
Abatement Date: 08/11/2017 4
Initial Penalty: $9,959.00
Current Penalty: $0.00
Issuance Date: 07/20/2017
Nr Instances: 5
Nr Exposed: 3
Related Event Code (REC): R
Gravity: 5
Report ID: 0213900
Contest Date: 08/04/2017
Final Order: 12/29/2021
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | J: ALJ Decision | 12/29/2021 | $0.00 | 08/11/2017 | Serious | |
Penalty | C: Contested | 08/07/2017 | $9,959.00 | 08/11/2017 | Serious | |
Penalty | Z: Issued | 07/20/2017 | $9,959.00 | 08/11/2017 | Serious |
Text For Citation: 01 Item/Group: 014A Hazard:
29 CFR 1910.219(c)(2)(ii): Shafting under bench machines was not enclosed by a stationary casing, or by a trough at sides and top or sides and bottom, as location requires: a) 9000 River Rd, Delair, NJ, 08110- Building 3, Sutton 1 Press: Employees performed work including, but not limited to, metal stretching, table manipulation, and cold saw operations on equipment including, but not limited to, the Sutton 1 press where rotating shafting were not completely guarded on the drive mechanisms under the table structures, occurred on or about 2/9/2017. b) 9000 River Rd, Delair, NJ, 08110- Building 6, Sutton 3 Press: Employees performed work including, but not limited to, metal stretching, table manipulation, and cold saw operations on equipment including, but not limited to, the Sutton 3 press where rotating shafting were not completely guarded on the drive mechanisms under the table structures, occurred on or about 2/9/2017. c) 9000 River Rd, Delair, NJ, 08110- Building 8, Sutton 4 Press: Employees performed work including, but not limited to, metal stretching, table manipulation, and cold saw operations on equipment including, but not limited to, the Sutton 4 press where rotating shafting were not completely guarded on the drive mechanisms under the table structures, occurred on or about 2/24/2017. d) 9000 River Rd, Delair, NJ, 08110- Building 9, BLH Press: Employees performed work including, but not limited to, metal stretching, table manipulation, and cold saw operations on equipment including, but not limited to, the BLH press where rotating shafting were not completely guarded on the drive mechanisms under the table structures, occurred on or about 2/9/2017. e) 9000 River Rd, Delair, NJ, 08110- Building 10, Danieli Press: Employees performed work including, but not limited to, metal stretching, table manipulation, and cold saw operations on equipment including, but not limited to, the Danieli press where rotating shafting were not completely guarded on the drive mechanisms under the table structures, occurred on or about 2/24/2017. NOTE: THE EMPLOYER IS REQUIRED TO SUBMIT ABATEMENT CERTIFICATION FOR THIS ITEM. FAILURE TO COMPLY WILL RESULT IN AN ADDITIONAL PENALTY OF $1000.00 IN ACCORDANCE WITH 29 CFR 1903.19.