Violation Detail
Standard Cited: 19100119 J04 I Process safety management of highly hazardous chemicals.
This violation item has been deleted.
Inspection Nr: 313008674
Citation: 01014
Citation Type: Serious
Abatement Status:
Initial Penalty: $4,500.00
Current Penalty:
Issuance Date: 10/13/2009
Nr Instances: 3
Nr Exposed: 10
Abatement Date: 11/06/2009
Gravity: 10
Report ID: 0213900
Contest Date: 10/28/2009
Final Order: 04/22/2010
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | R: Review Commission | 04/22/2010 | 11/06/2009 | Serious | ||
| Penalty | Z: Issued | 10/13/2009 | $4,500.00 | 11/06/2009 | Serious |
Text For Citation: 01 Item/Group: 014 Hazard: REFINERY
29 CFR 1910.119(j)(4)(i): Inspections and tests were not performed on process equipment to maintain its mechanical integrity: a) Nustar Asphalt Refining Co. LLC, Paulsboro facility, Unit 1 - The employer did not conduct inspections and testing on process equipment it identified as safeguards in the Unit 1 Process Hazard Analysis conducted in April 2009, Node 4. On or about 5/13/09. NOTE: IN ADDITION TO ABATEMENT CERTIFICATION, THE EMPLOYER IS REQUIRED TO SUBMIT ABATEMENT DOCUMENTATION FOR THIS ITEM, FAILURE TO COMPLY WILL RESULT IN AN ADDITIONAL PENALTY OF $1000.00 IN ACCORDANCE WITH 29 CFR 1903.19.CE