Violation Detail
Standard Cited: 19260451 F07 General requirements.
This violation item has been deleted.
Inspection Nr: 1068239.015
Citation: 01014
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $3,850.00
Current Penalty: $0.00
Issuance Date: 11/30/2015
Nr Instances: 3
Nr Exposed: 5
Abatement Date: 12/08/2015
Gravity: 5
Report ID: 0523300
Contest Date: 12/21/2015
Final Order: 04/09/2018
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 04/09/2018 | $0.00 | 12/08/2015 | Serious | |
| Penalty | F: Formal Settlement | 04/09/2018 | $3,230.00 | 12/14/2015 | Serious | |
| Penalty | C: Contested | 01/04/2016 | $5,390.00 | 12/14/2015 | Serious | |
| Penalty | C: Contested | 01/04/2016 | $3,850.00 | 12/08/2015 | Serious | |
| Penalty | Z: Issued | 11/30/2015 | $3,850.00 | 12/08/2015 | Serious | |
| Penalty | Z: Issued | 11/30/2015 | $5,390.00 | 12/14/2015 | Serious |
Text For Citation: 01 Item/Group: 014 Hazard:
29 CFR 1926.1060(a): The employer did not provide a training program for each employee using ladders and stairways, as necessary, which would enable each employee to recognize hazards related to ladders and stairways and train each employee in the procedures to be followed to minimize these hazards. Employees were not trained to recognize hazards associated with ladders, such as but not limited to, proper use of a ladder. ABATEMENT DOCUMENTATION IS REQUIRED FOR THIS ITEM IN ACCORDANCE WITH REQUIREMENTS OF 29 CFR 1903.19(d) 29 CFR 1926.451(f)(7): Scaffolds were not erected, moved, dismantled, or altered, by trained and experienced employees under the supervision and direction of a competent person qualified in scaffold erection, moving, dismantling or alteration: Such activities were not performed only by experienced and trained employees selected for such work by the competent person. Employees erecting, moving, dismantling, or altering single point suspension scaffolding inside the water tower were not under the direction and supervision of a competent person. ABATEMENT CERTIFICATION IS REQUIRED FOR THIS ITEM IN ACCORDANCE WITH REQUIREMENTS OF 29 CFR 1903.19(C).