Violation Detail
Standard Cited: 19100119 F01 I Process safety management of highly hazardous chemicals.
Inspection Nr: 314928060
Citation: 01013A
Citation Type: Serious
Abatement Status: X
Initial Penalty: $4,900.00
Current Penalty: $3,000.00
Issuance Date: 04/08/2011
Nr Instances: 1
Nr Exposed: 27
Abatement Date: 05/01/2012
Gravity: 10
Report ID: 0627700
Contest Date:
Final Order:
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | P: Petition to Mod Abatement | 11/07/2011 | $3,000.00 | 05/01/2012 | Serious | |
| Penalty | I: Informal Settlement | 04/27/2011 | $3,000.00 | 11/01/2011 | Serious | |
| Penalty | Z: Issued | 04/08/2011 | $4,900.00 | 04/27/2011 | Serious |
Text For Citation: 01 Item/Group: 013A Hazard: CHEMNEP
29 CFR 1910.119(f)(1): The employer did not develop and implement written operating procedures that provided clear instructions for safety conducting activities in each covered process consistentwith the process safety information and which addressed the elements listed in 29 CFR 1910.119(f)(1)(i)(A) through (f)(1)(i)(G): The employer has not developed and implemented written operating procedures that provided clear instructions for safely conducting activities in the various operating phases such as but not limited to Temporary Operations, Emergency Shutdown, Normal Shutdown, or Start-up following a turnaround, and or after an Emergency Shutdown. This violation occurred on or about October 20, 2010. Pursuant to 29 C.F.R. 1903.19, within ten (10) calendar days of the date of this citation, the employer must submit documentation showing that it is in compliance with the standard regarding operating procedures including steps for each operating phase. A method of abatement is to complete development and implementation of operating procedures that provide clear instructions for safely conducting activities involved in each phase of the process such as but not limited to Temporary Operations, Emergency Shutdown including conditions where emergency shutdown is required, Normal Shutdown, or Start-up following a turnaround, and or after an Emergency Shutdown as per 29 CFR 1910.119(f)(1)(i)(A) through (G).ugh