Violation Detail
Standard Cited: 19100119 D03 I G Process safety management of highly hazardous chemicals.
Inspection Nr: 451379.015
Citation: 01013
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $7,000.00
Issuance Date: 11/26/2012
Nr Instances: 3
Nr Exposed: 30
Abatement Date: 12/29/2012
Gravity: 5
Report ID: 0522500
Contest Date: 12/12/2012
Final Order: 03/10/2014
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 03/10/2014 | $7,000.00 | 12/29/2012 | Serious | |
| Penalty | C: Contested | 12/19/2012 | $0.00 | 12/29/2012 | Serious | |
| Penalty | Z: Issued | 11/26/2012 | $0.00 | 12/29/2012 | Serious |
Text For Citation: 01 Item/Group: 013 Hazard:
29 CFR 1910.119(d)(3)(i)(G): Process safety information. Information pertaining to the equipment in the process shall include: Material and energy balances for processes built after May 26, 1992: Information was not compiled regarding material and energy balances for processes, including but not limited to: a. The 44R reactor process (phosphites department): This process was put into place in January 2001. b. The 75R reactor process (phosphites department): This process was put into place in 2009. c. The 35R reactor process (phosphites department): The process chemistry was changed in response to the Main Street installation being disconnected from the 36R reactor and the 36R reactor process conversion to run 9228.
Translate