Standard Cited: 19100254 D06 Arc welding and cutting.
Inspection Nr: 1814753.015
Citation: 01013
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $6,620.00
Current Penalty: $6,620.00
Issuance Date: 06/09/2025
Nr Instances: 11
Nr Exposed: 3
Abatement Date: 06/20/2025
Gravity: 10
Report ID: 0111100
Contest Date:
Final Order: 07/01/2025
Related Event Code (REC): A
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 07/01/2025 | $6,620.00 | 06/20/2025 | Other | |
| Penalty | Z: Issued | 06/09/2025 | $6,620.00 | 06/20/2025 | Serious |
Text For Citation: 01 Item/Group: 013 Hazard:
29 CFR 1910.254(d)(6): Printed rules and instructions covering the operations of equipment supplied by the manufacturers were not strictly followed: Garage - The employer failed to ensure welding operations followed the manufacturer's operating instructions for the Lincoln Electric Power MIG 180 Dual Metal Inert Gas Welder, in the following instances: a) DO NOT WELD OR CUT containers or materials which previously been in contact with hazardous substances unless they are properly cleaned. b) REMOVE all potential fire hazards from the welding area. c) ALWAYS HAVE FIRE FIGHTING EQUIPMENT READY FOR IMMEDIATE USE AND KNOW HOW TO USE IT. d) WELDING AND CUTTING SPARKS CAN CAUSE FIRE OR EXPLOSION.