Violation Detail
Standard Cited: 19260858 C Removal of steel construction.
Inspection Nr: 1089845.015
Citation: 01013
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $2,800.00
Current Penalty: $1,400.00
Issuance Date: 01/13/2016
Nr Instances: 1
Nr Exposed: 4
Abatement Date: 02/29/2016
Gravity: 5
Report ID: 0213600
Contest Date: 01/21/2016
Final Order: 08/08/2016
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | J: ALJ Decision | 08/08/2016 | $1,400.00 | 02/29/2016 | Serious | |
Penalty | C: Contested | 01/26/2016 | $2,800.00 | 02/29/2016 | Serious | |
Penalty | Z: Issued | 01/13/2016 | $2,800.00 | 02/29/2016 | Serious |
Text For Citation: 01 Item/Group: 013 Hazard:
29 CFR 1926.858(c): Steel construction was not dismantled column length by column length, and tier by tier: a) On or about 8/27/15 at a demolition project located at 1111 Allen Street, Jamestown, New York; employees were demolishing a bridge between two buildings passing over a city street. The structure was not removed column length by column length. There were sections that were cantilevered beyond the nearest supporting column and support members removed prior to another span being completed. ABATEMENT CERTIFICATION REQUIRED