Standard Cited: 19100305 G01 IV A Wiring methods, components, and equipment for general use.
Inspection Nr: 1018385.015
Citation: 01013
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $3,600.00
Current Penalty: $1,800.00
Issuance Date: 07/13/2015
Nr Instances: 2
Nr Exposed: 5
Abatement Date: 08/06/2015
Gravity: 5
Report ID: 0524200
Contest Date:
Final Order: 07/21/2015
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 07/21/2015 | $1,800.00 | 08/06/2015 | Serious | |
Penalty | Z: Issued | 07/13/2015 | $3,600.00 | 08/06/2015 | Serious |
Text For Citation: 01 Item/Group: 013 Hazard:
29 CFR 1910.305(g)(1)(iv)(A): Flexible cords and/or cables were used as a substitute for the fixed wiring of a structure: a) Secondary Operations Area- The employer failed to provide permanent wiring where needed, such as running to the five Air Presses, and flexible cords were used as a substitute. b) Secondary Operations Area- The employer failed to provide permanent wiring where needed, such as running to the Surveillance Equipment, and flexible cords were used as a substitute. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.