Violation Detail
Standard Cited: 19100179 F06 II Overhead and gantry cranes.
Inspection Nr: 414289.015
Citation: 01012C
Citation Type: Serious
Abatement Date: 11/20/2012 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 10/29/2012
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC):
Gravity: 10
Report ID: 0336000
Contest Date: 11/23/2012
Final Order: 01/31/2013
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 01/31/2013 | $0.00 | 11/20/2012 | Serious | |
Penalty | C: Contested | 01/31/2013 | $0.00 | 11/20/2012 | Serious | |
Penalty | Z: Issued | 10/29/2012 | $0.00 | 11/20/2012 | Serious |
Text For Citation: 01 Item/Group: 012C Hazard:
29 CFR 1910.179(f)(6)(ii): Cab-operated crane(s), with cab on trolley, were not provided with bridge brake(s) of the holding type: A.) Vortex Recycling/P & H Overhead Crane - On or about 4/30/12 and at times prior thereto, P&H crane was operated with deficiencies identified in the February 2012 crane inspection report. Several of the items noted in the February 2012 crane inspection report were repeat items that were originally identified in the November 2010 crane inspection report. Deficiencies included but were not limited to speed control on auxiliary hoist, magnet cable lower cord grip, bridge brake not operating, main and auxiliary wire ropes with broken strands