Violation Detail
Standard Cited: 19100303 G02 II General.
Inspection Nr: 1565239.015
Citation: 01012C
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 05/12/2022
Nr Instances: 1
Nr Exposed: 8
Abatement Date: 02/22/2023
Gravity: 10
Report ID: 0524530
Contest Date: 05/31/2022
Final Order: 02/22/2023
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 02/22/2023 | $0.00 | 02/22/2023 | Serious | |
Penalty | C: Contested | 06/01/2022 | $0.00 | 06/08/2022 | Serious | |
Penalty | Z: Issued | 05/12/2022 | $0.00 | 06/08/2022 | Serious |
Text For Citation: 01 Item/Group: 012C Hazard:
29 CFR 1910.303(g)(2)(ii): In locations where electric equipment is likely to be exposed to physical damage, enclosures or guards shall be so arranged and of such strength as to prevent such damage: Mixing Department, Line 6 (Floor 2): On or about February 24, 2022 and times prior, an electrical control panel and an associated transformer box located near the mixer's weighing belt area (to the Northwest of the mixer) used to power the pneumatic lifting assist devices on the mixer's weight belt housed live parts greater than 50 volts. The electrical control panel was in use with a damaged and partially attached cover resulting in openings. The transformer box was in use with a damaged box containing openings.