Violation Detail
Standard Cited: 19100212 A03 General requirements for all machines.
Inspection Nr: 1441704.015
Citation: 01012A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $3,318.00
Issuance Date: 04/08/2020
Nr Instances: 7
Nr Exposed: 7
Abatement Date: 04/14/2020
Gravity: 5
Report ID: 0111700
Contest Date:
Final Order: 05/05/2020
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 05/05/2020 | $3,318.00 | 04/14/2020 | Serious | |
Penalty | Z: Issued | 04/08/2020 | $0.00 | 04/14/2020 | Serious |
Text For Citation: 01 Item/Group: 012A Hazard:
29 CFR 1910.212(a)(3): Point of operation guard were not provided: (a) R & D Dept. - The Brown & Sharpe 21B/5 was inadequately guarded. (b) R & D Dept. - The Maximum Die Cutter SR-2048 was inadequately guarded. (c) Small Parts Dept. - The W.H. Nichols SR-16 Cutter was inadequately guarded. (d) Small Parts Dept. - The W.H. Nichols SR-1353 Cutter was inadequately guarded. (e) Foundry Cell 1 - The W.H. Nichols #8 abrasive disc cut off saw was not adequately guarded. (f) Foundry Cell 2 - The W.H. Nichols abrasive disc cut off saw was not adequately guarded. (g) Legacy Foundry - The W.H. Nichols abrasive disc cut off saw was not adequately guarded.