Violation Detail
Standard Cited: 19100303 B02 General.
Inspection Nr: 1626768.015
Citation: 01012
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $15,469.00
Current Penalty: $7,735.00
Issuance Date: 03/23/2023
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 01/31/2024
Gravity: 10
Report ID: 0522000
Contest Date: 04/17/2023
Final Order: 03/04/2024
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 03/04/2024 | $7,735.00 | 01/31/2024 | Serious | |
Penalty | C: Contested | 04/17/2023 | $15,469.00 | 05/09/2023 | Serious | |
Penalty | Z: Issued | 03/23/2023 | $15,469.00 | 05/09/2023 | Serious |
Text For Citation: 01 Item/Group: 012 Hazard:
29 CFR 1910.303(b)(2): Installation and use. Listed or labeled equipment shall be installed and used in accordance with any instructions included in the listing or labeling. a) On or about November 8, 2022 in the Solids Department at the 1000 Hydromat moulder, employees were exposed to electrical hazards from the 480 volt Rittal motor control cabinet due to the lockout point not being used to lockout the motor control cabinet as the lockout point was no longer present on the outside of the cabinet.