Violation Detail
Standard Cited: 19100219 C03 Mechanical power-transmission apparatus.
Inspection Nr: 1187531.015
Citation: 01012
Citation Type: Serious
Abatement Date: 04/27/2017 2
Initial Penalty: $9,054.00
Current Penalty: $9,054.00
Issuance Date: 04/12/2017
Nr Instances: 3
Nr Exposed: 6
Related Event Code (REC):
Gravity: 5
Report ID: 0625400
Contest Date: 04/26/2017
Final Order: 07/17/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 07/17/2018 | $9,054.00 | 04/27/2017 | Serious | |
Penalty | C: Contested | 05/02/2017 | $9,054.00 | 04/27/2017 | Serious | |
Penalty | Z: Issued | 04/12/2017 | $9,054.00 | 04/27/2017 | Serious |
Text For Citation: 01 Item/Group: 012 Hazard:
29 CFR 1910.219(c)(3): Vertical or inclined shafting seven 7 feet or less from floor or working platform was not enclosed with stationary casing(s): On or about November 7, 2016, in the casting department, employees are required to clean, inspect, maintain and unclog vent holes on the system three mixing tank on a daily basis and were exposed to three unguarded, rotating shafts. Employees exposed to the hazard of being caught-in the rotating shafts.