Violation Detail
Standard Cited: 19100334 A02 II Use of equipment.
Inspection Nr: 1162442.015
Citation: 01012
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $9,799.00
Current Penalty: $7,000.00
Issuance Date: 01/11/2017
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 01/27/2017
Gravity: 5
Report ID: 0627700
Contest Date:
Final Order: 02/27/2017
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 02/27/2017 | $7,000.00 | 01/27/2017 | Serious | |
Penalty | Z: Issued | 01/11/2017 | $9,799.00 | 01/27/2017 | Serious |
Text For Citation: 01 Item/Group: 012 Hazard:
29 CFR 1910.334(a)(2)(ii): There was a defect or evidence of damage that could have exposed employees to injury and the defective or damaged item was not removed from service: The employer does not ensure that electrical were maintained free from cuts and freys. This violation was observed on or about July 19, 2016 in the trim department at the facility, exposing employees to electrical hazards. Pursuant to 29 CFR 1903.19, within ten (10) calendar days of the date of this citation, the employer must submit documentation describing the steps taken to ensure that all flexible cords and/or cables are maintained in safe operating condition.