Violation Detail
Standard Cited: 19100254 D09 III Arc welding and cutting.
Inspection Nr: 1212211.015
Citation: 01011D
Citation Type: Serious
Abatement Date: 04/10/2017 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 03/30/2017
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC):
Gravity: 5
Report ID: 0625400
Contest Date:
Final Order: 05/01/2017
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 05/01/2017 | $0.00 | 04/10/2017 | Serious | |
Penalty | Z: Issued | 03/30/2017 | $0.00 | 04/10/2017 | Serious |
Text For Citation: 01 Item/Group: 011D Hazard:
29 CFR 1910.254(d)(9)(iii): Cables with damaged insulation or exposed bare conductors were not replaced: On or about February 21, 2017, in building 1, an employee was using a Miller welder to weld metal products for a feeder where the ground lead (electrode), which still carries DC voltage was damage, exposing the internal copper conductors. Employees exposed to the an electrical shock hazard.