Violation Detail
Standard Cited: 19100303 F02 General.
Inspection Nr: 1375672.015
Citation: 01011B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 06/07/2019
Nr Instances: 1
Nr Exposed: 20
Abatement Date: 07/25/2019
Gravity: 1
Report ID: 0112000
Contest Date:
Final Order: 07/09/2019
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 07/09/2019 | $0.00 | 07/25/2019 | Serious | |
Penalty | Z: Issued | 06/07/2019 | $0.00 | 07/25/2019 | Serious |
Text For Citation: 01 Item/Group: 011B Hazard:
29 CFR 1910.303(f)(2): Each service, feeder, and branch circuit, at its disconnecting means or overcurrent device, was not legibly marked to indicate its purpose, nor located and arranged so the purpose was evident: Building 3, Main Aisle near QC Office: On, or about, March 14, 2019, twenty six of the breakers located in Panel 3I were not labelled to indicate their purpose.