Violation Detail
Standard Cited: 19100305 G01 IV D Wiring methods, components, and equipment for general use.
Inspection Nr: 1308095.015
Citation: 01011B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 09/21/2018
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 10/03/2018
Gravity: 5
Report ID: 0316700
Contest Date: 10/12/2018
Final Order: 01/09/2019
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 01/09/2019 | $0.00 | 10/03/2018 | Serious | |
Penalty | C: Contested | 10/15/2018 | $0.00 | 10/03/2018 | Serious | |
Penalty | Z: Issued | 09/21/2018 | $0.00 | 10/03/2018 | Serious |
Text For Citation: 01 Item/Group: 011B Hazard:
29 CFR 1910.305(g)(1)(iv)(D): Flexible cords and cables were attached to building surfaces; a) Machine Shop - A powered orange flexible cord used to power a fluorescent shop light, was observed secured to a steel chain hanging from a metal I beam on or before April 11, 2018. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.