Violation Detail
Standard Cited: 19100305 D02 Wiring methods, components, and equipment for general use.
Inspection Nr: 1721955.015
Citation: 01011A
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $16,131.00
Current Penalty: $16,131.00
Issuance Date: 07/18/2024
Nr Instances: 2
Nr Exposed: 5
Related Event Code (REC):
Gravity: 10
Report ID: 0419400
Contest Date: 08/06/2024
Final Order: 11/27/2024
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | J: ALJ Decision | 11/27/2024 | $16,131.00 | Serious | ||
Penalty | C: Contested | 10/10/2024 | $16,131.00 | Serious | ||
Penalty | Z: Issued | 07/18/2024 | $16,131.00 | Serious |
Text For Citation: 01 Item/Group: 011A Hazard:
29 CFR 1910.305(d)(2): Panelboards were not mounted in cabinets, cutout boxes, or enclosures designed for the purpose and/or were not dead front: (a) Coating mill - On or about February 13, 2024, the employer did not ensure that the three-phase electrical cabinet that provides power for the plasma cutter, and other electrical equipment in the area was closed and the dead front panel was in place, exposing employees to an electrical hazard.