Standard Cited: 19100219 D01 Mechanical power-transmission apparatus.
Inspection Nr: 1100641.015
Citation: 01011A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $2,400.00
Current Penalty: $1,200.00
Issuance Date: 03/10/2016
Nr Instances: 3
Nr Exposed: 2
Abatement Date: 03/22/2016
Gravity: 5
Report ID: 0316400
Contest Date: 04/04/2016
Final Order: 07/18/2016
Related Event Code (REC): C
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 07/18/2016 | $1,200.00 | 03/22/2016 | Serious | |
Penalty | C: Contested | 04/07/2016 | $2,400.00 | 03/22/2016 | Serious | |
Penalty | Z: Issued | 03/10/2016 | $2,400.00 | 03/22/2016 | Serious |
Text For Citation: 01 Item/Group: 011A Hazard:
29 CFR 1910.219(d)(1): Pulley(s) with part(s) seven feet or less from the floor or work platform were not guarded in accordance with the requirements specified in 29 CFR 1910.219(m) and (o): (a) Head Saw: On or about October 21, 2015, and times prior, pulleys located 23 inches from the floor and operating at 550 RPM were not guarded. (b) Edger: On or about October 21, 2015, and times prior, pulleys located 24 inches from the floor and operating at 1,000 RPM were not guarded. (c) Planer: On or about October 21, 2015, and times prior, pulleys located on the front and on the side of the planer, 12 inches up to 16 inches from the floor and operating at 3,000 RPM were not guarded.