Violation Detail
Standard Cited: 19100305 G01 IV A Wiring methods, components, and equipment for general use.
Inspection Nr: 936564.015
Citation: 01011
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $1,200.00
Current Penalty: $720.00
Issuance Date: 12/23/2013
Nr Instances: 2
Nr Exposed: 8
Abatement Date:
Gravity: 1
Report ID: 0112000
Contest Date:
Final Order: 01/09/2014
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 01/09/2014 | $720.00 | Serious | ||
| Penalty | Z: Issued | 12/23/2013 | $1,200.00 | Serious |
Text For Citation: 01 Item/Group: 011 Hazard:
29 CFR 1910.305(g)(1)(iv)(A): Flexible cords and/or cables were used as a substitute for the fixed wiring of a structure: A. Processing Area, Opti-Line: On, or about, August 28, 2013, an extension cord was used to energize the moisture valves provided on the air receiver tanks located under the ceramic and amber optical sortation stations. B. Processing Area, Benefication Line: On, or about, August 28, 2013, an extension cord was used to energize the blower unit located on the recycle conveyor.