Violation Detail
Standard Cited: 19100305 A01 I Wiring methods, components, and equipment for general use.
Inspection Nr: 1044850.015
Citation: 01011
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $3,300.00
Current Penalty: $1,650.00
Issuance Date: 09/02/2015
Nr Instances: 1
Nr Exposed: 4
Abatement Date: 09/25/2015
Gravity: 1
Report ID: 0729700
Contest Date:
Final Order: 09/22/2015
Related Event Code (REC): C
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 09/22/2015 | $1,650.00 | 09/25/2015 | Serious | |
Penalty | Z: Issued | 09/02/2015 | $3,300.00 | 09/25/2015 | Serious |
Text For Citation: 01 Item/Group: 011 Hazard:
29 CFR 1910.305(a)(1)(i): Metal raceways, cable armor, and other metal enclosures for conductors were not connected to all boxes, fittings, and cabinets to provide effective electrical continuity: Employees engaged in production and maintenance activities on the roof top of Baked Plant were exposed to electrical shock hazards in that the metal raceway for the electrical conductors connected for the Hansen valve was broken exposing live conductors. The broken raceway no longer effectively bonded to ensured electrical continuity. 29 CFR 1903.19(c)(1) requires certification that the abatement of the above violation is complete.