Standard Cited: 19100305 J02 V Wiring methods, components, and equipment for general use.

Inspection Nr: 1126756.015

Citation: 01010C

Citation Type: Other

Abatement Status: Quick Fix

Initial Penalty: $0.00

Current Penalty: $0.00

Issuance Date: 07/15/2016

Nr Instances: 1

Nr Exposed: 4

Abatement Date:

Gravity:

Report ID: 0830600

Contest Date:

Final Order: 08/04/2016

Related Event Code (REC):

Emphasis:


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty I: Informal Settlement 08/04/2016 $0.00   Other  
Penalty Z: Issued 07/15/2016 $0.00   Serious  

Text For Citation: 01 Item/Group: 010C Hazard:

29 CFR 1910.305(j)(2)(v): A receptacle installed outdoors in a location protected from the weather or in other damp locations did not have an enclosure for the receptacle that was weatherproof when the receptacle was covered (attachment plug cap not inserted and receptacle covers closed): a) Support column near South rail dock crane: On or about March 4, 2016, and at times prior, workers were exposed to electrical shock hazards where a receptacle outlet in a damp/wet location was missing the weatherproof cover. Abatement Note: Employer completed abatement during inspection.

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.