Violation Detail
Standard Cited: 19100179 F04 IX Overhead and gantry cranes.
Inspection Nr: 191122.015
Citation: 01010B
Citation Type: Serious
Abatement Date: 08/17/2012 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 07/27/2012
Nr Instances: 1
Nr Exposed: 50
Related Event Code (REC):
Gravity: 10
Report ID: 0524200
Contest Date: 08/16/2012
Final Order: 01/10/2014
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 01/10/2014 | $0.00 | 08/17/2012 | Serious | |
Penalty | C: Contested | 08/17/2012 | $0.00 | 08/17/2012 | Serious | |
Penalty | Z: Issued | 07/27/2012 | $0.00 | 08/17/2012 | Serious |
Text For Citation: 01 Item/Group: 010B Hazard:
29 CFR 1910.179(f)(4)(ix): Brakes on the trolleys and bridges of cranes did not have ample thermal capacity for the frequency of operation required by the service to prevent impairment of functions from overheating. a) Forge Shop 2- The employer failed to ensure that all trolleys and bridges for cranes at the facility, such as Crane #T2480, were equipped with brakes that had an ample thermal capacity for the frequency of operation that was required by the service to prevent impairment of functions from overheating. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.