Violation Detail
Standard Cited: 19100305 A02 II Wiring methods, components, and equipment for general use.
Inspection Nr: 1131364.015
Citation: 01010A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $4,410.00
Current Penalty: $2,646.00
Issuance Date: 06/28/2016
Nr Instances: 1
Nr Exposed: 10
Abatement Date: 07/07/2016
Gravity: 10
Report ID: 0627100
Contest Date:
Final Order: 07/18/2016
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 07/18/2016 | $2,646.00 | 07/07/2016 | Serious | |
Penalty | Z: Issued | 06/28/2016 | $4,410.00 | 07/07/2016 | Serious |
Text For Citation: 01 Item/Group: 010A Hazard:
29 CFR 1910.305(a)(2)(ii): Temporary wiring shall be removed immediately upon completion of the project or purpose for which the wiring was installed. On or about March 7, 2016 and there prior, temporary wiring was used indefinitely on the work floor.