Violation Detail
Standard Cited: 19100303 B07 IV General.
Inspection Nr: 1126756.015
Citation: 01010A
Citation Type: Serious
Abatement Status: Quick Fix
Initial Penalty: $4,675.00
Current Penalty: $3,000.00
Issuance Date: 07/15/2016
Nr Instances: 1
Nr Exposed: 4
Abatement Date:
Gravity: 5
Report ID: 0830600
Contest Date:
Final Order: 08/04/2016
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 08/04/2016 | $3,000.00 | Serious | ||
Penalty | Z: Issued | 07/15/2016 | $4,675.00 | Serious |
Text For Citation: 01 Item/Group: 010A Hazard:
29 CFR 1910.303(b)(7)(iv): There were damaged parts that could adversely affect safe operation or mechanical strength of the equipment, such as parts that are broken, bent, cut, or deteriorated by corrosion, chemical action, or overheating: a) South rail dock crane: On or about March 4, 2016, and at times prior, crane wiring and equipment did not comply with Subpart S per 1910.179(g)(1)(i), in that workers were exposed to injuries related to electrical fires, shock, and electrocution where the crane cab heater electrical box had loose and missing insulation, evidence of arcing, and cross-threaded terminal screws. b) Rail dock: On or about March 4, 2016, and at times prior, workers were exposed to electrical shock hazards where an outdoor electrical outlet was damaged. Abatement Note: Employer completed abatement during inspection.