Standard Cited: 19100119 L04 Process safety management of highly hazardous chemicals.
Inspection Nr: 314927559
Citation: 01010
Citation Type: Serious
Abatement Status: X
Initial Penalty: $5,000.00
Current Penalty: $3,500.00
Issuance Date: 03/14/2011
Nr Instances: 1
Nr Exposed: 14
Abatement Date: 04/16/2011
Gravity: 10
Report ID: 0627700
Contest Date:
Final Order:
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 03/24/2011 | $3,500.00 | 04/16/2011 | Serious | |
Penalty | Z: Issued | 03/14/2011 | $5,000.00 | 04/16/2011 | Serious |
Text For Citation: 01 Item/Group: 010 Hazard: REFINERY
29 CFR 1910.119(l)(4): A change covered by 29 CFR 1910.119(l) resulted in a change in the process safety information required by 29 CFR 1910.119(d) and the process information was not updated: On or about September 14, 2010, and at times prior thereto, the employer did not update #2 Platformer piping and instrument diagrams (P&IDs). P&ID MF-45075 depicting the Chloride Injection Tank and Methanol Injection Tank and associated piping and equipment was not concurrent with actual field conditions.