Violation Detail
Standard Cited: 19100269 L08 II Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1749405.015
Citation: 01010
Citation Type: Serious
Abatement Status:
Initial Penalty: $6,452.00
Current Penalty: $6,452.00
Issuance Date: 11/20/2024
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 12/03/2024
Gravity: 10
Report ID: 0213100
Contest Date: 12/19/2024
Final Order:
Related Event Code (REC): A
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | C: Contested | 12/19/2024 | $6,452.00 | 12/03/2024 | Serious | |
Penalty | Z: Issued | 11/20/2024 | $6,452.00 | 12/03/2024 | Serious |
Text For Citation: 01 Item/Group: 010 Hazard:
29 CFR 1910.269(l)(8)(ii): For each employee exposed to hazards from electric arcs, the employer did not make a reasonable estimate of the incident heat energy to which the employee could be exposed: (a) Mount Ida Hydro Station, Control room level: On or about May 21, 2024, employees conducting maintenance on an Allis Chalmers MA-250C circuit breaker in a 4160-volt switchgear housing experienced an arc flash when the breaker contacted an energized cell during racking-in. The employer did not make a reasonable estimate of the incident heat energy to which the employee could be exposed, such as when racking breakers in high voltage switchgear.