Violation Detail
Standard Cited: 19100333 A01 Selection and use of work practices
Inspection Nr: 1690989.015
Citation: 01010
Citation Type: Serious
Abatement Date: 02/15/2024 2
Initial Penalty: $11,292.00
Current Penalty: $8,469.00
Issuance Date: 02/09/2024
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC): A
Gravity: 10
Report ID: 0626700
Contest Date:
Final Order: 03/11/2024
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 03/11/2024 | $8,469.00 | 02/15/2024 | Serious | |
Penalty | Z: Issued | 02/09/2024 | $11,292.00 | 02/15/2024 | Serious |
Text For Citation: 01 Item/Group: 010 Hazard:
29 CFR 1910.333(a)(1): Live parts to which an employee may be exposed were not deenergized before the employee worked on or was near to them: a) On or about August 14, 2023, energy control procedures were not utilized to de-energize electrical circuits prior to maintenance.